Question: A project manager discovers that his team has neglected to complete the network diagram for the project. The network diagram is shown in Figure. However,
A project manager discovers that his team has neglected to complete the network diagram for the project. The network diagram is shown in Figure. However, the project manager has some information available, specifically that each activity, labeled A–G, has a different duration between one and seven weeks. Also, the slack time for each of the activities is known as shown below:
Duration (weeks): 1, 2, 3, 4, 5, 6, 7
Slack time (weeks): 0, 0, 0, 3, 6, 8, 8
-1.png)
Using the clues provided below, determine the duration of each activity as well as the early start, early finish, latest start, and latest finish times for each activity.
Clues
1. There exists only one critical path, and it is the largest possible number given the possible durations shown.
2. Activity E has the smallest amount of slack that is greater than zero.
3. The early finish (EF) time for activity A is four weeks, and this does not equal the latest finish (LF) time. (Note: There is no negative slack in the network.)
4. The slack in activity C is eight weeks.
5. The duration of activity F is greater than the duration of activity C by at least twoweeks.
-2.png)
START FINISH Activity Duration Early Start Early Finish Latest Start Latest Finish
Step by Step Solution
3.27 Rating (165 Votes )
There are 3 Steps involved in it
Activity Duration ES EF LS LF A 3 0 3 4 7 B 7 0 7 0 7 C 5 0 5 2 7 D 2 7 9 11 13 E 6 7 13 7 13 F 1 5 ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
93-B-M-L-P-M (847).docx
120 KBs Word File
