Question: A project manager discovers that his team has neglected to complete the network diagram for the project. The network diagram is shown in Figure. However,

A project manager discovers that his team has neglected to complete the network diagram for the project. The network diagram is shown in Figure. However, the project manager has some information available, specifically that each activity, labeled A–G, has a different duration between one and seven weeks. Also, the slack time for each of the activities is known as shown below:

Duration (weeks): 1, 2, 3, 4, 5, 6, 7

Slack time (weeks): 0, 0, 0, 3, 6, 8, 8


A project manager discovers that his team has


Using the clues provided below, determine the duration of each activity as well as the early start, early finish, latest start, and latest finish times for each activity.
Clues
1. There exists only one critical path, and it is the largest possible number given the possible durations shown.
2. Activity E has the smallest amount of slack that is greater than zero.
3. The early finish (EF) time for activity A is four weeks, and this does not equal the latest finish (LF) time. (Note: There is no negative slack in the network.)
4. The slack in activity C is eight weeks.
5. The duration of activity F is greater than the duration of activity C by at least twoweeks.

A project manager discovers that his team has


START FINISH Activity Duration Early Start Early Finish Latest Start Latest Finish

Step by Step Solution

3.27 Rating (165 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Activity Duration ES EF LS LF A 3 0 3 4 7 B 7 0 7 0 7 C 5 0 5 2 7 D 2 7 9 11 13 E 6 7 13 7 13 F 1 5 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

93-B-M-L-P-M (847).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!