Question: Perform a financial analysis for a project where the projected costs and benefits are spread over five years with the following data: Estimated costs are
Perform a financial analysis for a project where the projected costs and benefits are spread over five years with the following data:
Estimated costs are $100,000 in Year 1 and $25,000 each for years 2, 3, 4, and 5.
Estimated benefits are $0 in Year 1 and $80,000 each for years 2, 3, 4, and 5.
Use a discount rate of 8%
1. In n Excel spreadsheet to show costs and benefits over the five-year period.
2. Calculate cash flow.
3. Show the discount factor.
4. Show discounted costs and discounted benefits.
5. Calculate and clearly display the NPV (Net Present Value), ROI (Return on Investment), and year in which payback (break-even point) occurs.
Step by Step Solution
3.38 Rating (151 Votes )
There are 3 Steps involved in it
Sure Lets perform the financial analysis for the project based on the given data Heres how you can d... View full answer