Question: Perform a financial analysis for the following project and answer the following related questions. Projected costs for this project are spread over four years as
Perform a financial analysis for the following project and answer the following related questions. Projected costs for this project are spread over four years as follows:
- Estimated costs are $200,000 in Year 1 and $50,000 each in Years 2, 3, and 4. - Estimated benefits are $0 in Year 1 and $160,000 each year in Years 2, 3, and 4. - Use an 10% discount rate.
What is the NPV of this project (rounded to nearest dollar)?