Question: Perform a Multi - Attribute Decision analysis using the following utility table and k values. Which combination of Overrun Time and Extra Cost is the

Perform a Multi-Attribute Decision analysis using the following utility table and k values. Which combination of Overrun Time and Extra Cost is the best choice?
Time Overrun
Utility
Cost
Utility
0
1
33000
1
2.6
0.88
39000
0.87
3
0.44
61000
0.8
5.4
0
102000
0.44
135000
0
k1=
0.85
k2=
0.77
In this question, k1 represents the probability to make the manager against overrun time
k2 represents the probability to make the manager against extra cost
The value of k3 will be
Using the decision tree shown, determine the multi-attribute utilities at each terminal node for each combination of time and cost.
Use the letters below each cell to identify. Report each response to four decimals. Include a leading zero ( for example 0.2341)
A=
B=
C=
D=
E=
Calculate the responses for each probability node shown.
Use the letters below each cell to identify. Report each response to four decimals. Include a leading zero ( for example 0.2341)
F=
G=
The combination of Overrun Time and Extra Cost that is the best choice will be overrun time and $ extra cost
Compute the Ranked Order Centroid for 10 Attributes
Report the weights to two decimal places. (Include a leading zero for responses between 0 and 1, for example 0.87)
Attribute Weight
1
2
3
4
5
6
7
8
9
10

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!