Question: Perform a Multi-Attribute Decision analysis using the following utility table and k values. Which combination of Overrun Time and Extra Cost is the best choice?



Perform a Multi-Attribute Decision analysis using the following utility table and k values. Which combination of Overrun Time and Extra Cost is the best choice? Time Utility Overrun Cost Utility O 33000 1 2.6 0.88 39000 0.87 3 0.44 61000 0.8 5.4 0 102000 0.44 135000 0 k1 = 0.85 k2= 0.77Time 102000 0.61 A F 0.39 2.6 135000 B 0 33000 0.23 C 3 39000 G 0.5 D 0.27 5.4 61000 EQuestion 15 3 pts In this question, k1 represents the probability to make the manager against overrun time k2 represents the probability to make the manager against extra cost The value of k3 will be