Question: Perform a network analysis on the following table: Activity Duration Immediate predecessor activies A 2 B 3 C 4 A D 5 A & B

Perform a network analysis on the following table:

Activity Duration Immediate predecessor activies
A 2
B 3
C 4 A
D 5 A & B
E 8 C & D
F 3 D
G 2 F
H 3 G