Question: Perform an earned value analysis for the following project. The data in the table covers the first weeks of the project, and all activities were

Perform an earned value analysis for the following project. The data in the table covers the first weeks of the project, and all activities were started as planned.
\table[[Activity,\table[[Immediate],[Predecessors]],\table[[Normal Time],[(weeks)]],Budget ($),% Complete,\table[[Actual Cost],[($)]]],[A,-,2,240,100,120],[B,A,4,400,60,180],[C,A,3,300,40,200],[D,C,5,250,0,0]]
Hint: you may not need a network
Earned value is
2- Cost variance (CV)
Schedule variance (SV)=
EAC for the project is
Percent completion (PC) is
Planned Percent Complete (PPC) is
What is your conclusion on project status?
MGg50261_2zeet _ing
1173160g6 anc.
 Perform an earned value analysis for the following project. The data

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!