Question: Perform resource allocation for the given project using the series method. The maximum resource availability is 5 Electricians ( E ) . Solve the problem

Perform resource allocation for the given project using the series method. The maximum
resource availability is 5 Electricians (E). Solve the problem using the following conditions:
Use the following rule: - Earliest Late Start then Least Total Float to break a tie.
- Project start at Day 1.
Activity Duration Followers Resource Demands
(Electricians)
A 2 B, C 5 E
B 3 D, E, F 2 E
C 3 F 3 E
D 4 G, H 2 E
E 4 H 3 E
F 7 H 1 E
G 3 I 2 E
H 5 J 2 E
I 6 J 3 E
J 3-2 E
DELIVERABLES:
- A single resource allocation table for this problem.
- An AOA diagram of these activities showing precedence relationships.
RUBRIC:
- Incorrect CPM calculations (-2 points)
- Exceeding maximum resource (-1 point)
- Incorrect logic/predecessors/successors (-.5 points)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!