Question: Perssimistic Activity Predecessor B 9 9 11 10 8 Brain Break Optimistic Most likely duration 4 5 4 8 6 7 5 9 4 6

Perssimistic Activity Predecessor B 9 9 11 10 8 Brain Break Optimistic Most likely duration 4 5 4 8 6 7 5 9 4 6 2 8 5 9 3 6 5 6 A A D BE C G FH D E F G H K 9 10 8 9 . . 1a. Calculate the durations for each of the activities using the beta distribution (durations in weeks) 16. Draw the network diagram using the weighted average and determine the earliest time the project would be completed Cc. Determine the activities on the critical path & calculate the standard deviation for the activities on the critical path . 47 TADOS
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
