Question: Use the following Table to answer the questions. Activity Predecessor Duration (weeks) A - 8 B - 8 C A 6 D A 6 E

Use the following Table to answer the questions.

ActivityPredecessorDuration (weeks)
A-8
B-8
CA6
DA6
EB4
FD, E3
GC4
HF, G6

Use the following Table to answer the questions.ActivityPredecessorDuration (weeks)A-8B-8CA6DA6EB4FD, E3GC4HF, G6 282 points What is the project duration? 18 24 O 23 O25 29 2 points What is the critical path for this schedule?O ACGH ABDFH O BEFH ADFH 30 3 points What is theEarly Start, Early Finish for Activity E? O 9, 15 11, 158, 12 O 8, 143 points What is the Late Start, LateFinish for Activity F? 14, 18 8,12 11, 15 15, 18 2points What is the Total Float for Activity B? O 3 1

28 2 points What is the project duration? 18 24 O 23 O 25 29 2 points What is the critical path for this schedule? O ACGH ABDFH O BEFH ADFH 30 3 points What is the Early Start, Early Finish for Activity E? O 9, 15 11, 15 8, 12 O 8, 143 points What is the Late Start, Late Finish for Activity F? 14, 18 8,12 11, 15 15, 18 2 points What is the Total Float for Activity B? O 3 1 2 2 points What is the Free Float for Activity F? 2 3 O 1 34 3 points What is the Expected duration for this PERT schedule? O 24.33 23.13 O 25.17 O 26 35 2 points What is the expected duration for Activity B 2 O 5.17 O 1 O 3 36 2 points What is the critical path of this PERT schedule? O CFEH O CEG O ABD O CFH3 points What is the Early Start, Early Finish for Activity D? 12.5, 16.67 14, 18.33 10, 15.50 9, 17 3 points What is the variance for Activity (3? 0.44 .11 2.25 1.00 3 points What is the Late Start, Late Finish for Activity F? 13, 17 9, 17 14, 18.33 9, 14 4 points What is the probability that the project can be completed in 26 days? 100% 14.2% 85.8% 84.10% 3 points What is the probability that the project can be completed in 22 days? 6.80% 84.10% 50.0% 11.80% 3 points What is the total variance for the critical path? 6.00 2.44 3.36 1.00 2 points 5 What is the duration of the project under normal conditions? Type your answer... 2 points 5 What is the total normal project cost for completing the project under normal conditions? Type your answer... 3 points 5 What activities are on the critical path? BDCG BDEF ACG BEF 2 points What is the cost unit for Activity E? Type your answer... 2 points What is the cost unit for Activity E? Type your answer... 2 points What is the crash unit cost for Activity D? 500 4500 625 O 3 points The owner wants to shorten the total duration by 2 weeks. Which activity should be shortened? F B O c E 3 points What will be the crash cost for this shortening by two weeks this activity? Type your answer... 3 points What will be the crash cost for this shortening by two weeks this activity? Type your answer... 3 points What is the total crash cost if we were to crash the whole schedule without doing any easing of activities? Type your

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!