Question: PERT 2 Fall 2021 ACTIVITY PREC. ACT. TIME ESTIMATES (days) to tml tp te A ----- 1 3 5 B A 2 2 2 C
PERT 2 Fall 2021
ACTIVITY PREC. ACT. TIME ESTIMATES (days)
to tml tp te
A ----- 1 3 5
B A 2 2 2
C A 1 1 1
D B 0 0 0
E C, D 2 3 4
F C, D 1 1 1
G F 1 1 1
H E, G 2 2 2
1) Construct a PERT network.
[NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.]
2) Compute 68% and 99% CI.
3) Find the completion time and the standard deviation () for the project round off the standard deviation to the nearest hundredth: two decimal places.
4) What is the likelihood of this project being completed earlier than 10 days?
5) Between 9 and 12 days?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts