Question: PERT 2 Fall 2021 ACTIVITY PREC. ACT. TIME ESTIMATES (days) to tml tp te A ----- 1 3 5 B A 2 2 2 C

PERT 2 Fall 2021

ACTIVITY PREC. ACT. TIME ESTIMATES (days)

to tml tp te

A ----- 1 3 5

B A 2 2 2

C A 1 1 1

D B 0 0 0

E C, D 2 3 4

F C, D 1 1 1

G F 1 1 1

H E, G 2 2 2

1) Construct a PERT network.

[NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.]

2) Compute 68% and 99% CI.

3) Find the completion time and the standard deviation () for the project round off the standard deviation to the nearest hundredth: two decimal places.

4) What is the likelihood of this project being completed earlier than 10 days?

5) Between 9 and 12 days?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!