Question: PERT 3 ACTIVITY PREC. ACT. TIME ESTIMATES (days) t o t ml t p t e A ----- 2 3 4 B ----- 4 7

PERT 3

ACTIVITY PREC. ACT. TIME ESTIMATES (days)

to tml tp te

A ----- 2 3 4

B ----- 4 7 10

C A 1 2 3

D B 2 5 8

E B 4 6 8

F C, D 1 1 1

G E 2 3 4

H F, G 1 1 1

4) What is the completion time at 68% and 99.7 % confidence levels?

5) What is the likelihood of this project being completed later than 17 days?

6) Between 16 and 18 days?

Please respond question 4, 5, and 6