PERT 3
ACTIVITY PREC. ACT. TIME ESTIMATES (days)
to tml tp te
A ----- 2 3 4
B ----- 4 7 10
C A 1 2 3
D B 2 5 8
E B 4 6 8
F C, D 1 1 1
G E 2 3 4
H F, G 1 1 1
4) What is the completion time at 68% and 99.7 % confidence levels?
5) What is the likelihood of this project being completed later than 17 days?
6) Between 16 and 18 days?
Please respond question 4, 5, and 6