Question: PERT TEST 2 Fall 2022 ACTIVITY PREC. ACT. TIME ESTIMATES (days) t o t ml t p t e A --- 1 1 1 B
PERT TEST 2 Fall 2022
ACTIVITY PREC. ACT. TIME ESTIMATES (days)
t o t ml t p t e
A --- 1 1 1
B A 2 3 4
C A 4 7 10
D B 1 2 3
E C 2 5 8
F C 4 6 8
G D, E 1 1 1
H F 3 4 5
I H, G 1 2 3
1) Construct a PERT network.
[NOTE: This is the most crucial part of the exercise. Make sure you have the correct
network before proceeding to the next sections.]
2) By using ES, EF, LF, LS, find the slack of each activity and the critical path.
3) Find the completion time and the standard deviation () for the project round off
the standard deviation to the nearest hundredth:
two decimal places.
4) What is the completion time at 68% and 95 % confidence levels?
5) What is the likelihood of this project being completed earlier than 18 days?
6) Between 17 and 20 days?
Please show your work, the question wont be answer unless you show how you got to the final result. This question will be posted several times in order to comply with the website one question at the time requirement but all answer are required for the final result, the question in BOLD letter is the specific one for each post.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
