Question: PERT - actually it is a CPM problem a PERT chart. This is a chart of a project consisting of six tasks. In the first

PERT - actually it is a CPM problem
a PERT chart. This is a chart of a project consisting of six tasks. In the first table you see all the tasks listed along with completion time and task dependencies. Note not all the tasks need a prior task to be completed, that is they are independent.
The second table lists the paths or completion steps for sub-tasks and tasks dependent on them. This project could be anything you like, building a house, remodeling a house, building a car manufacturing plant, planning a wedding, etc.
Which path is the critical or most important path? Why is it the Critical Path and what is the significance of this path?
Thanks in advance!
40 1 = 1 wk t = 3 wk C t = 2 wk 20 50 D 10 1 - 3 wk B 1 = 4 wk E t = 2 wk 30 NetMBA.com Task Task Time in Weeks Previous Tasks A B A D E F WNNWAw) A B AC PATH 1 Tasks ACF AD Path Times 3+1+3 = 7 Weeks 3+2=5 Weeks 4+2= 6 Weeks WN BEStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts