Question: Pertorm earned value analysis using the details presented below and calculate BCWS , BCWP , ACWP, Schedule Performance Index and Cost Performance Index The project
Pertorm earned value analysis using the details presented below and calculate BCWS BCWP ACWP, Schedule Performance Index and Cost Performance Index
The project status at the end of working days is presented below:
i Activity A : done, used workersday at the cost of Rs day
ii Activity B: done, used workersday at the cost of Rs day
iii Activity C : done, used workers day at the cost of Rs per day
iv Activity D: not yet started;
BCWS at the project level as on status date:
A
B
C
D
ACWP at the project level as of status date:
A
B
C
D
SPI and CPI values are
ASPI is and CPI is
BSPI is and CPI is
CSPI is and CPI is
DSPI is and CPI is
BCWP at the project level as on
status date:
A
B
C
D
CHOOSE THE RIGHT OPTIONS IN EACH ONE QUESTION RELATED TO PROJECT MANAGENT
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock