Question: Peter, a project manager, completed a change request to seek approval for the change from the project sponsor. Peter's change request should include all of

Peter, a project manager, completed a change request to seek approval for the change from the project sponsor.
Peter's change request should include all of the following elements EXCEPT __________.
a.)
a statement of support from the project sponsor
b.)
a plan to adapt to the change
c.)
a description of the change
d.)
an impact statement

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer