Question: Phase 1 : NSL g 1 = 2 2 . 4 s Phase 2 : NST / R g 2 = 3 2 . 0

Phase1: NSL g1=22.4s Phase2: NST/R g2=32.0s Phase3: EWL g3=27.2s Phase4: EWT/R g4=38.4. g1,g2,g3,g4 is effective green time. If the critical flow ratio for NST/R is 0.20 and the intersection is operating at the optimum cycle time. A) calculate the cycle time B) calculate the actual green time C) draw the light sequence diagram. Inter-green oeriod I=4s Yellow time Y=2 sec

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!