Question: Pieces produced per cycle: 8 Average measured cycle time: 8 . 3 6 min Average measured effort time per cycle: 4 . 6 2 min
Pieces produced per cycle:
Average measured cycle time: min
Average measured effort time per cycle: min
Average rapid traverse time: min
Average cutting time power feed: min
Performance rating: percent
Allowance machine time: percent
Allowance effort time: percent
CHAPTER Time Study
The operator works on the job a full h day and produces pieces. How many standard hours does the operator earn? What is the operator's efficiency for the h day?