Question: Pieces produced per cycle: 8 Average measured cycle time: 8 . 3 6 min Average measured effort time per cycle: 4 . 6 2 min

Pieces produced per cycle: 8
Average measured cycle time: 8.36min
Average measured effort time per cycle: 4.62min
Average rapid traverse time: 0.08min
Average cutting time power feed: 3.66min
Performance rating: 115 percent
Allowance (machine time): 10 percent
Allowance (effort time): 15 percent
CHAPTER 10 Time Study
The operator works on the job a full 8-h day and produces 380 pieces. How many standard hours does the operator earn? What is the operator's efficiency for the 8-h day?