Question: plan it Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of

plan it
Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table. Job Processing Time (days) Due Date (days) A 5 11 B 6 16 3 19 D 4 10 Share E 2. 9 Using the earliest due date (EDD) rule, the average lateness for the five jobs is: O a. more than -6 but less than or equal to -2 days. O b. more than-2 but less than or equal to 2 days. Doc. more than 2 but less than or equal to 6 days. O d. more than 4 but less than or equal to 8 daysStep by Step Solution