Question: Planned value is: Select one: O A The cumulative total costs incurred in accomplishing the various project work packages O B. The real budgeted value

Planned value is: Select one: O A The cumulative total costs incurred in accomplishing the various project work packages O B. The real budgeted value of the work that has actually been performed to date. O C. The total budget for the project. OD. A cost estimate of the budgeted resources across the project's life cycle