Question: multiple choice 1 Divide the EV by the PV you will get the: a. Budget efficiency index. b. Cost performance index. c. Schedule performance index.

multiple choice

1 Divide the EV by the PV you will get the:

a.

Budget efficiency index.

b.

Cost performance index.

c.

Schedule performance index.

d.

Budgeted cost at completion index.

2 Creating a budget from work breakdown structure and costs for each work package, and then adding these costs together is:

a.

Zero-based budgeting.

b.

Top-down budgeting.

c.

Activity-based budgeting.

d.

Bottom-up budgeting

3 A plan that identifies the allocated resources, the project's goals, and the schedule that allows an organization to achieve those goals is:

a.

The risk management plan.

b.

The work breakdown structure.

c.

The project budget.

d.

The statement of work.

3 Function point analysis is a system for estimating the size of software projects based on the number of lines of code a typical programmer can write in a day.

a.

False

b.

True

4 This is a variable cost :

a.

Construction Materials.

b.

Staff Salaries.

c.

Capital equipment.

d.

Health insurance.

5 The earned value of a project is the cumulative total costs incurred in accomplishing the various work packages.

a.

False

b.

True

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!