Question: multiple choice 1 Divide the EV by the PV you will get the: a. Budget efficiency index. b. Cost performance index. c. Schedule performance index.
multiple choice
1 Divide the EV by the PV you will get the:
a.
Budget efficiency index.
b.
Cost performance index.
c.
Schedule performance index.
d.
Budgeted cost at completion index.
2 Creating a budget from work breakdown structure and costs for each work package, and then adding these costs together is:
a.
Zero-based budgeting.
b.
Top-down budgeting.
c.
Activity-based budgeting.
d.
Bottom-up budgeting
3 A plan that identifies the allocated resources, the project's goals, and the schedule that allows an organization to achieve those goals is:
a.
The risk management plan.
b.
The work breakdown structure.
c.
The project budget.
d.
The statement of work.
3 Function point analysis is a system for estimating the size of software projects based on the number of lines of code a typical programmer can write in a day.
a.
False
b.
True
4 This is a variable cost :
a.
Construction Materials.
b.
Staff Salaries.
c.
Capital equipment.
d.
Health insurance.
5 The earned value of a project is the cumulative total costs incurred in accomplishing the various work packages.
a.
False
b.
True