Question: ple answer again A Project has been defined to contain the following list of activities along with their required times for completion Activity No. Immediate

 ple answer again A Project has been defined to contain the

following list of activities along with their required times for completion Activity

ple answer again

A Project has been defined to contain the following list of activities along with their required times for completion Activity No. Immediate Activity Time (weeks) Predecessors Collect requirement:s Analyze processes Analyze data Design processes Design data Design screens Design reports Program Test and document Install 2 4. 2 4 5 3,4 4,5 6,7 10 8,9 Table 1