Question: please also answer: Based on normal time and observed times, Charlenes work performance should be rated as: a Faster than normal b Slower than normal

please also answer: Based on normal time and
please also answer:

Based on normal time and observed times, Charlenes work performance should be rated as:

a Faster than normal

b Slower than normal

c Same as normal

Suppose Charlene Brewster has times (in seconds) of 8.5, 8.7, 8.2, 8.5, 8.8, 8.6 and a performance rating of 105%. The normal time for this operation = seconds (round your response to two decimal places)