Question: Please and answer the question. Solved Problem #3 9.98 Required Time (weeks) Cost Activity A B D E F Immediate Predecessors none A A B

Please and answer the question.
Solved Problem #3 9.98 Required Time (weeks) Cost Activity A B D E F Immediate Predecessors none A A B B.C E.F D.E HG Normal 4 3 2 5 1 3 4 4 6 Crash 2 2 1 3 1 2 2 1 5 Normal $10.000 $6.000 $4.000 $14.000 $9.000 $7.000 $13.000 $11.000 $20.000 Crash $11.000 $9.000 $6.000 $18.000 $9.000 $8.000 $25.000 $18.000 $29.000 H 1 a. What are the critical path and the estimated completion time? D. To shorten the project by three weeks, which tasks would be shortened and what would the final total project cost be? 5 D B 3 6 2 3Step by Step Solution