Question: Please and answer the question. Solved Problem #3 9.98 Required Time (weeks) Cost Activity A B D E F Immediate Predecessors none A A B

Please and answer the question. Solved Problem #3

Please and answer the question.

Solved Problem #3 9.98 Required Time (weeks) Cost Activity A B D E F Immediate Predecessors none A A B B.C E.F D.E HG Normal 4 3 2 5 1 3 4 4 6 Crash 2 2 1 3 1 2 2 1 5 Normal $10.000 $6.000 $4.000 $14.000 $9.000 $7.000 $13.000 $11.000 $20.000 Crash $11.000 $9.000 $6.000 $18.000 $9.000 $8.000 $25.000 $18.000 $29.000 H 1 a. What are the critical path and the estimated completion time? D. To shorten the project by three weeks, which tasks would be shortened and what would the final total project cost be? 5 D B 3 6 2 3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!