Question: please answer 1 of 2 - + Automatic Zoom ACTIVITY View as Text Download Predecessor Estimate in weeks > > Start C Start 6 B

 please answer 1 of 2 - + Automatic Zoom ACTIVITY View

please answer

as Text Download Predecessor Estimate in weeks > > Start C Start

1 of 2 - + Automatic Zoom ACTIVITY View as Text Download Predecessor Estimate in weeks > > Start C Start 6 B Start P Start A C.B.P U P A R A N U End T.R.N Using the table above, draw the network diagram and answer the questions. When you have completed answering the questions, do a forward/backward pass 1. How many paths are in the network, and what are they? 2. What is the critical path and its duration? Activate Window 3. What is the float on activity U? Go to Settings to activ 4. What is the impact to the project if activity B takes three weeks longer than planned? 27"C Mostly cloudy ~ / 10 0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Economics Questions!