Question: please answer 12.5, 12.6, 12.7, 12.8 and 12.9 using the information given For Problems 5-9, consider a project with the following information: Activity Duration Predecessors


please answer 12.5, 12.6, 12.7, 12.8 and 12.9 using the information given
For Problems 5-9, consider a project with the following information: Activity Duration Predecessors A A B C D B IT mono 5 7 9 5 7 6 4 7 B C,D D C E, F, G G H Activity Duration ES EF LS LF Float 5 5 0 5Step by Step Solution