Question: please answer a and b The following project has three independent paths as shown in the project network diagram. The deadline to complete this project
The following project has three independent paths as shown in the project network diagram. The deadline to complete this project is 46 days. a) What is the probability that this project will be delared? Name: b) What is the probability that activity F alone will take between 44 and 46 dey