Question: Please show all steps Question 5 (8 marks) b) What is the probability that activity F alone will take between 44 and 46 days? The

Please show all steps Question 5 (8 marks) b)Please show all steps

Question 5 (8 marks) b) What is the probability that activity F alone will take between 44 and 46 days? The following project has three independent paths as shown in the project network diagram. The deadline to complete this project is 46 days. Activity Optimistic Time (days) Most Likely Time (days) Pessimistic Expected Variance Time Time of (days) (days) Activity D Start End 11 A 10 16 28 B 20 28 42 F 18 30 42 D 15 15 15 E 1 2 3 F 42 45 48 a) What is the probability that this project will be delayed