Question: please answer all parts Consider the following table and PERT diagram to answer the following questions: Description Task Must Follow Time (Weeks) Draw osta Draw
please answer all parts

Consider the following table and PERT diagram to answer the following questions: Description Task Must Follow Time (Weeks) Draw osta Draw decision tre,e Revise trec 4 None Revie utrut desig 10 rire se cases Desipn clatatase I H. E. and G 20 40 60 30 g) h) (5%) which activities have slack associated with them? Explain. (5%) What is the total length of the project? Explain. (5%) Suppose revising the tree took an extra week, what kind of impact on the length of the project would that have? Explain