Question: please answer all parts will rate (a) Construct the project network. (Submit a file with a maximum size of 1MB.) No file chosen This answer

please answer all parts will rate
(a) Construct the project network. (Submit a file with a maximum size of 1MB.) No file chosen This answer has not been graded yet. (b) Based solely on the critical path, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.) (c) Using all paths through the project network, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.) (d) Should you use the estimate in (b) or (c)? The probability estimate from (b) based on the critical path is more accurate. The probability estimate from (c) based on both paths is more accurate. The probability estimates from (b) and (c) are equal
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts