Question: Please answer all thank you so much :) Considering the below information about a software engineering project, is the project over budget or under budget?

Please answer all thank you so much :)Please answer all thank you so much :)Please answer all thank you so much :)

Considering the below information about a software engineering project, is the project over budget or under budget? Planned Value (PV) = 8,000 Earned Value (EV) = 10,000 Actual Cost (AC) = 6,000 Project term: 24 months over budget under budget on track Considering the below information about a software engineering project, the SPI is: Planned Value (PV) = 4,000 Earned Value (EV) = 8,000 Actual Cost (AC) = 6,000 Project term: 24 months 75% 50% 2