Question: Please answer all!!! This is all one question and fill in the boxes Office Automation, Inc., developed a proposal for introducing a new computerized office

Please answer all!!! This is all one question and fill in the boxes

Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities.

Time (weeks) Cost ($1000s)
Activity Description Immediate Predecessor Normal Crash Normal Crash
A Plan needs 10 8 30 70
B Order equipment A 8 6 120 150
C Install equipment B 10 7 100 160
D Set up training lab A 7 6 40 50
E Conduct training course D 10 8 50 75
F Test system C, E 3 3 60

(b) Develop an activity schedule.

Activity Earliest Start Latest Start Earliest Finish Latest Finish Slack
A
B
C
D
E
F

(c) What are the critical activities? (Enter your answers as a comma-separated list.)

________

What is the expected project completion time (in weeks)?_____ weeks

(d) Assume that the company wants to complete the project in six months or 26 weeks. What is the amount of crash time (in weeks) for each activity that minimizes cost?

(A, B, C, D, E) = (_________)

(e) Develop an activity schedule for the crashed project.

Activity Earliest Start Latest Start Earliest Finish Latest Finish Slack
A
B
C
D
E
F

(f)What added project cost (in thousands of dollars) is required to meet the six-month completion time? ________ thousands of dollars

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!