Question: please answer and show work for the entire question If the project is completed in normal duration, overhead cost is $3700 If the project is

please answer and show work for the entire question
please answer and show work for the entire
please answer and show work for the entire
If the project is completed in normal duration, overhead cost is $3700 If the project is completed in 30 days, overhead cost is $3300 If the project is completed in 26 days, overhead cost is $3100 If the project is completed at its minimum duration, overhead cost is $2900 Calculate total cost per duration and define which will be the optimal duration of the project