Question: please answer as soon as possible Use the information below to answer the following questions). The following decision tree is partially completed for a company

Use the information below to answer the following questions). The following decision tree is partially completed for a company that is deciding to build a large or small facility for a new product that will face demand that is strong or weak The company has an option to perform a market survey that will cost $4,000 that will predict a strong or weak market. The payoffs for each combination of facility size and demand are also shown Strong 0.65 $18,000 Large Weak $6,000 Strong 0.65 $10,000 Small Strong Survey Weak $1.000 Strong 0.75 0.6 $18,000 Weak Survey Large Weak $6,000 Strong 0.75 510,000 Small Weak $1,000 Given the survey will predict a strong market, the expected monetary value of building a large facility is 57 200 $6,500 $10.800 $9,600