Question: Please answer ASAP! will upvote! thanks An assembly-line process has six tasks, as listed in the table below: Four workers ( S1,S2,S3, and S4) are
An assembly-line process has six tasks, as listed in the table below: Four workers ( S1,S2,S3, and S4) are staffed to this assembly line, and the assignment of tasks to each worker is as follows: - S1 does Task 1. - S2 does Tasks 2 and 3. - S3 does Tasks 4. - S4 does Tasks 5 and 6. For the following questions, we assume that the process is operating at full capacity. (a) Which worker is the bottleneck of the process? What is the process capacity in [units/hour]? (1 point) (b) What is the idle time of each worker in [minutes]? (c) Assume a wage rate of $18 per hour. What is the direct labor cost in [\$/unit]