Question: Please answer both the questions 24 and 25 24. An activity on node network ( AON ) has an early start time of 10 days,

Please answer both the questions 24 and 25
24. An activity on node network ( AON ) has an early start time of 10 days, a duration of 5 days, and late finish time of 14 days. Calculate the slack or float time for this activity 4 days 1 day 2 days 10 days Question 25 2 pts 25. An activity on node network (AON) has an early start time of 10 days, a duration of 5 days, and late finish time of 14 days. Does this activity lie on the critical path of the network? No Yes
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
