Question: Please answer both the questions 24 and 25 24. An activity on node network ( AON ) has an early start time of 10 days,

Please answer both the questions 24 and 25 24. An activity on

Please answer both the questions 24 and 25

24. An activity on node network ( AON ) has an early start time of 10 days, a duration of 5 days, and late finish time of 14 days. Calculate the slack or float time for this activity 4 days 1 day 2 days 10 days Question 25 2 pts 25. An activity on node network (AON) has an early start time of 10 days, a duration of 5 days, and late finish time of 14 days. Does this activity lie on the critical path of the network? No Yes