Question: please answer c and d with reasons We have a process shown in the right figure. (M1 M4 are names for four machines. The numbers

 please answer c and d with reasons We have a process

shown in the right figure. (M1 M4 are names for four machines.please answer c and d with reasons

We have a process shown in the right figure. (M1 M4 are names for four machines. The numbers are activity times in minutes). Consider a schedule: schedule a job on M1 every 10 minutes, starting at time 0; schedule a job on M2 every 5 minutes starting at time 0. Jobs finished on M1 go to M4; jobs finished on M2 go to M3. M1 M3 M2 M4 10