Question: Please answer for Question No 2 & 3 1. The table below defines the precedence relationships and element times for a new assembled product. (a)

Please answer for Question No 2 & 3
1. The table below defines the precedence relationships and element times for a new assembled product. (a) Construct the precedence diagram for this job. (b) Using largest candidate rule, assign work elements to stations. (c) Compute the balance delay for your solution. Work element 1 2 3 4 5 6 7 8 9 10 T. (min) 0.5 0.3 0.8 0.2 0.1 0.6 0.4 0.5 0.3 0.6 Immediate predecessors 1 1 2 2 3 4,5 3,5 7,8 6,9 2. Solve the previous problem but use the Kilbridge and Wester method in part (b) 3. Solve the previous problem but use the ranked positional weights method in part (b)Step by Step Solution