Question: PLEASE, ANSWER IN COMPUTER TYPING, NO HAND WRITTING 2. Calculate the number of kanbans required for the following four components at the ABC Com- pany

PLEASE, ANSWER IN COMPUTER TYPING, NO HAND WRITTING
2. Calculate the number of kanbans required for the following four components at the ABC Com- pany in problem 1. Component W X Y Z 900 250 1,200 2 hours 5 hours Daily usage Lead time Container size Safety stock 1 hour 50 units 350 3 hours 20 units 25 units 40 units 25 percent 20 percent 15 percent 10 percentStep by Step Solution