Question: Please answer Part C - Thank you Consider the following data for a project to install a new server at the Northland Pines High School:


Please answer Part C - Thank you
Consider the following data for a project to install a new server at the Northland Pines High School: Immediate Predecessors Activity Time (days) 4 4 3 Activity B D E F G H 1 J 3 1 6 2 6 5 A B B B, C DE F F G, HI a. Choose the correct network diagram below. e SI b. Calculate the critical path for this project, The critical path is A-B-F-H-J and the project duration is 25 days. (Enter your response as a whole number.) c. How much slack is in each of the activities G, H, and I? Activity Activity Time (days) G 2 On critical path? Slack (days) H 6 1 5Step by Step Solution