Question: Consider the following data for a project to install a new server at the Northland Pines High School: Immediate Predecessor(s) Activity A B D E

Consider the following data for a project toConsider the following data for a project to

Consider the following data for a project to install a new server at the Northland Pines High School: Immediate Predecessor(s) Activity A B D E F Activity Time (days) 4 5 4 3 1 5 3 A A B B B, C D, E F F G, H, 1 4 3 6 c. How much slack is in each of the activities G, H, and I? Activity Activity Time (days) 3 On critical path? Slack (days) G 4 3