Question: Please, answer question 3 using the Gantt Chart and writing an explanation. I uploaded questions 1 and 2 in order to support information for question
Please, answer question 3 using the Gantt Chart and writing an explanation. I uploaded questions 1 and 2 in order to support information for question 3.


Exercises 1. Consider a project with the accompanying Gantt chart. Stella is your only electri- cal engineer and she is responsible for activities 3 and 4, which overlap. Level the project so that Stella is only working a maximum of 8 hours each day. What would the new Gantt chart look like? What would be the new project completion date? Consider a project with the following Gantt chart to answer exercises 2 and 3. ID Task Task Name Duration Jan 5, 20 SIMIT Jan 12, 20 Jan 19, 20 WTF S S MTWTFS SIM Mode * 1 2 3 Stella Activity 1 Activity 2 Activity 3 Activity 4 Activity 5 Activity 6 2 days 3 days 5 days 3 days 2 days 2 days 4 Stella 5 6 2. Bjorn and Thor are plumbers who have been scheduled to work on the construc- tion of a new school building. Just before the start of the project, Bjorn broke his arm and cannot work on the project. Now Thor has to handle his own activities as well as Bjorn's. Level the project Gantt chart so that Thor is responsible for activi- ties 3, 4, 6, and 7. What is the new estimated completion date for the project? ID Task Name a Task Mode Feb 17, 19 Feb 24, 19 Mar 3, 19 TEISS MIT W T F S S M T W T F S S MTWTF 1 2 3 Bjorn 4 Thor Activity 1 activity 2 Activity 3 activity 4 Activity 5 Activity 6 Activity 7 Activity 8 5 T 6 Bjorn 7 * Thor 8 3. Suppose instead of assigning Bjorn's work to Thor, you have the opportunity to hire two new plumbers to perform Bjorn tasks (shortening them by 50 percent). What would the new project estimated completion date be? Show your work. Exercises 1. Consider a project with the accompanying Gantt chart. Stella is your only electri- cal engineer and she is responsible for activities 3 and 4, which overlap. Level the project so that Stella is only working a maximum of 8 hours each day. What would the new Gantt chart look like? What would be the new project completion date? Consider a project with the following Gantt chart to answer exercises 2 and 3. ID Task Task Name Duration Jan 5, 20 SIMIT Jan 12, 20 Jan 19, 20 WTF S S MTWTFS SIM Mode * 1 2 3 Stella Activity 1 Activity 2 Activity 3 Activity 4 Activity 5 Activity 6 2 days 3 days 5 days 3 days 2 days 2 days 4 Stella 5 6 2. Bjorn and Thor are plumbers who have been scheduled to work on the construc- tion of a new school building. Just before the start of the project, Bjorn broke his arm and cannot work on the project. Now Thor has to handle his own activities as well as Bjorn's. Level the project Gantt chart so that Thor is responsible for activi- ties 3, 4, 6, and 7. What is the new estimated completion date for the project? ID Task Name a Task Mode Feb 17, 19 Feb 24, 19 Mar 3, 19 TEISS MIT W T F S S M T W T F S S MTWTF 1 2 3 Bjorn 4 Thor Activity 1 activity 2 Activity 3 activity 4 Activity 5 Activity 6 Activity 7 Activity 8 5 T 6 Bjorn 7 * Thor 8 3. Suppose instead of assigning Bjorn's work to Thor, you have the opportunity to hire two new plumbers to perform Bjorn tasks (shortening them by 50 percent). What would the new project estimated completion date be? Show your work
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts