Question: please answer question 5 Project Schedule Management 2 TABLE 6 - 3 Network diagram data for a large project table [ [ Activity ,

please answer question 5Project Schedule Management
2
TABLE 6-3 Network diagram data for a large project
\table[[Activity,Initial Node,Final Node,Estimated Duration],[A,1,2,10],[B,1,3,12],[C,1,4,8],[D,2,3,4],[E,2,5,8],[F,3,4,6],[G,4,5,4],[H,4,6,8],[I,5,6,6],[J,5,8,12],[K,6,7,8],[L,7,8,10]]
Enter the information from Exercise 2 into Project 2016. View the network diagram and task schedule table to see the critical path and float or slack for each activity. Print the Gantt chart and network diagram views and the task schedule table. Write a short paper that interprets this information for someone unfamiliar with project schedule management.
Enter the information from Exercise 3 into Project 2016. View the network diagram and task schedule table to see the critical path and float or slack for each activity. Print the Gantt chart and network diagram views and the task schedule table. Write a short paper that interprets this information for someone unfamiliar with project schedule management.
 please answer question 5Project Schedule Management 2 TABLE 6-3 Network diagram

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!