Question: please answer question d to g. Thank you. Crane Enterprises Ltd. has entered into a contract beginning in February 2020 to build two warehouses for

please answer question d to g. Thank you.

Crane Enterprises Ltd. has entered into a contract beginning in February 2020 to build two warehouses for Atlantis Structures Ltd. The contract is a non-cancellable fixed price contract for $ 9.7 million. The following data pertain to the construction period (all figures in thousands).

2020 2021 2022

Costs for the year

$ 4,140 5,060 700

Estimated costs to complete

5,060 800 -0-

Progress billings for the year (non-refundable)

3,815 4,485 1,400

Cash collected for the year

3,350 4,535 1,815

a) Using the percentage-of-completion method, calculate the percent complete for 2020 and 2021.

b) Calculate the amount of revenue to be recognized in 2020 and 2021.

c) Calculate the construction costs to be expensed in 2021.

d)Prepare the journal entry at December 31, 2021, to record long-term contract revenues, expenses, and losses for 2021

e)What is the balance in the Contract Asset/Liability account at December 31, 2020 and 2021?

f)Show how the construction contract would be reported on the SFP and the income statement for the year ended December 31, 2021.

g)Assume that Crane uses the zero-profit or completed-contract method. What would be the journal entry recorded on December 31, 2021?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!