Question: PLEASE ANSWER QUESTIONS 4 - 1 0 Problem 6 - 1 1 ( Algo ) Money Laundry has 1 4 washers and 1 2 dryers.

PLEASE ANSWER QUESTIONS 4-10
Problem 6-11(Algo)
Money Laundry has 14 washers and 12 dryers. All orders are first sent to wash and then to dry. It takes, on average, 40 minutes to wash one order and 23 minutes to dry.
What is the capacity of the washing stage?
Note: Round your answer to 2 decimal places.
What is the capacity of the drying stage?
Note: Round your answer to 2 decimal places.
Identify the bottleneck.
multiple choice 1
Washer
Dryer
What is the capacity of Money Laundry?
Note: Round your answer to 2 decimal places.
Money Laundry would like to increase the capacity by buying one more machine, should they buy a washer or a dryer?
multiple choice 2
Washer
Dryer
The manager, Mr. Money, decided not to buy a machine. He still has 14 washers and 12 dryers. The manager estimates that, on average, Money Laundry receives eight orders every hour. The manager also finds that, on average, there are three orders in the washing stage and five orders in the drying stage.
What is the utilization of washers, on average?
Note: Round your answer to 2 decimal places.
What is the utilization of dryers, on average?
Note: Round your answer to 2 decimal places.
On average, how long does it take an order to finish the washing process, from the time the order is received?
Note: Round your answer to 2 decimal places.
On average, how long does it take an order to finish the drying process, from the time the order finishes the washing process?
Note: Round your answer to 2 decimal places.
On average, how long does an order stay in Money Laundry?
Note: Round your answer to 2 decimal places.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!