Question: PLEASE ANSWER QUESTIONS 4 - 1 0 Problem 6 - 1 1 ( Algo ) Money Laundry has 1 4 washers and 1 2 dryers.
PLEASE ANSWER QUESTIONS
Problem Algo
Money Laundry has washers and dryers. All orders are first sent to wash and then to dry. It takes, on average, minutes to wash one order and minutes to dry.
What is the capacity of the washing stage?
Note: Round your answer to decimal places.
What is the capacity of the drying stage?
Note: Round your answer to decimal places.
Identify the bottleneck.
multiple choice
Washer
Dryer
What is the capacity of Money Laundry?
Note: Round your answer to decimal places.
Money Laundry would like to increase the capacity by buying one more machine, should they buy a washer or a dryer?
multiple choice
Washer
Dryer
The manager, Mr Money, decided not to buy a machine. He still has washers and dryers. The manager estimates that, on average, Money Laundry receives eight orders every hour. The manager also finds that, on average, there are three orders in the washing stage and five orders in the drying stage.
What is the utilization of washers, on average?
Note: Round your answer to decimal places.
What is the utilization of dryers, on average?
Note: Round your answer to decimal places.
On average, how long does it take an order to finish the washing process, from the time the order is received?
Note: Round your answer to decimal places.
On average, how long does it take an order to finish the drying process, from the time the order finishes the washing process?
Note: Round your answer to decimal places.
On average, how long does an order stay in Money Laundry?
Note: Round your answer to decimal places.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock