Question: please answer The actulles described by the following table are given for the Howard Corporation in Kansas Time Immediate Time immediate Time Activity (in weeks)

please answer
please answer The actulles described by the
The actulles described by the following table are given for the Howard Corporation in Kansas Time Immediate Time immediate Time Activity (in weeks) Predecessor(s) Activity in weeks) Predecessorts) Activity on weeks) Predecessor(s) . D 6 B G C.F. E 10 B H 5 D C F 5 1 4 G, H This exercise contain only parts and The activities on the critical path are A-B-E-G-I The total project completion time for Howent Corporation is weeks Enter your response as a whole number) C