Question: The activities described by the following table are given for the Duplaga Corporation. Activity Time ( in weeks ) Immediate Predecessor ( s ) Activity
The activities described by the following table are given for the Duplaga Corporation.
Activity
Time
in weeks
Immediate Predecessors
Activity
Time
in weeks
Immediate Predecessors
Activity
Time
in weeks
Immediate Predecessors
A
minus
D
B
G
E F
B
A
E
B
H
D
C
A
F
C
I
G H
This exercise contains only parts b and c
Part
b The activities on the critical pathLOADING... are