Question: The activities described by the following table are given for the Duplaga Corporation. Activity Time ( in weeks ) Immediate Predecessor ( s ) Activity

The activities described by the following table are given for the Duplaga Corporation.
Activity
Time
(in weeks)
Immediate Predecessor(s)
Activity
Time
(in weeks)
Immediate Predecessor(s)
Activity
Time
(in weeks)
Immediate Predecessor(s)
A
8
minus
D
6
B
G
5
E, F
B
6
A
E
9
B
H
5
D
C
3
A
F
5
C
I
4
G, H
This exercise contains only parts b and c.
Part 2
b) The activities on the critical pathLOADING... are