Question: please answer the d question 3. (VALUE 20) The house construction project is presented in the following table Activities Time (days) Predecessor Activities A 20
please answer the d question
3. (VALUE 20) The house construction project is presented in the following table Activities Time (days) Predecessor Activities A 20 B C D E F G H 1 J K You are asked: 25 30 55 40 45 20 50 35 20 10 A B B C D E, F F.G H, I J a. Make a network diagram with AON or AOA b. Determine the lenath of time for project completion c. Determine the value of ES, EF, LS, LF and slack time for each activity d. Determine the activities on the critical path