Question: 3. (VALUE 20) The house construction project is presented in the following table Activities Time (days) Predecessor Activities A 20 B C D E F

3. (VALUE 20) The house construction project is
3. (VALUE 20) The house construction project is presented in the following table Activities Time (days) Predecessor Activities A 20 B C D E F G H 1 J K You are asked: 25 30 55 40 45 20 50 35 20 10 A B B C D E, F F.G H, I J a. Make a network diagram with AON or AOA b. Determine the lenath of time for project completion c. Determine the value of ES, EF, LS, LF and slack time for each activity d. Determine the activities on the critical path

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!